1 B
Ref: PMBOK® guide 5th ed. Page 364.
2 D
Ref: PMBOK® guide 5th ed. Page 171.
Triangular Distribution Time estimate = (Optimistic time estimate + Most likely time estimate + Pessimistic time estimate) / 3
(2+6+4)/3=4 which is not an option in the above list.”
3 C
Ref: PMBOK® guide 5th ed. Page 364.
4 B
Ref: PMBOK® guide 5th ed. Page 366.
5 D
Ref: PMBOK® guide 5th ed. Page 376.
6- 4(A, C)
Ref: PMBOK® guide 5th ed. Page 404.
7 B
Ref: PMBOK® guide 5th ed. Page 408.
8- 3 (All of the above)
9 D
Ref: PMBOK® guide 5th ed. Page 235.
10 D
Ref: PMBOK® guide 5th ed. Page 235.
11 B
Ref: PMBOK® guide 5th ed. Page 237.
Explanation: Pareto principle identifies the key issues that should be fixed to resolve 80% of the problems. In this case, if the first 3 issues are fixed, that fixes 80% of the support issues.
12 D
Ref: PMBOK® guide 5th ed. Page 250, https://en.wikipedia.org/wiki/Mean_time_between_failures
13 B
Ref: PMBOK® guide 5th ed. Page 238.
14 A
Ref: PMBOK® guide 5th ed. Page 116.
15 B
Explanation: The time taken for each of the paths is as follows:
ABCDE?5d+5d+2d+1d=13d
AFGCDE?2d+3d+1d+2d+1d=7d
AHIDE?3d+6d+3d+1d=13d
Since AHIDE and ABCDE take the same time to complete and are the longest paths, they are the critical paths for this project. Total float is 0 on the critical path.
16 A
Ref: PMBOK® guide 5th ed. Page 362.
17 A
18- 1(A and B)
Ref: PMBOK® guide 5th ed. Page 179.
19- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 181.
20 C
Ref: PMBOK® guide 5th ed. Page 221.
EAC = AC + [(BAC – EV) / (CPI × SPI)]
EAC=1000+[(1200-900)/(1.2*0.9)]=$1277.77
21 A
Ref: PMBOK® guide 5th ed. Page 364.
22 B
Ref: PMBOK® guide 5th ed. Page 364.
23- 3(C, D, A)
Ref: PMBOK® guide 5th ed. Page 351.
24 B
Ref: PMBOK® guide 5th ed. Page 364.
25 B
Ref: PMBOK® guide 5th ed. Page 364.
Explanation:
Initial estimate=$5000
Incentive promised if performance conditions are met=$1000
Overage=20% of $5000=$1000
Agreement between buyer and seller was to share the departure from original estimate at a pre-determined rate of 70 (buyer)/30 (seller).
70% of overage=$700
Seller to pay=Initial estimate+Incentive+70% of overage =$5000+$1000+$700=$6700
26 B
Ref: PMBOK® guide 5th ed. Page 364.
Explanation:
Overage=20% of $5000=$1000
Agreement between buyer and seller was to share the departure from original estimate at a pre-determined rate of 70 (buyer)/30 (seller).
30% of overage=$300 which seller has to bear.
27 C
Ref: PMBOK® guide 5th ed. Page 364.
28 D
Ref: PMBOK® guide 5th ed. Page 364.
29 B
Ref: PMBOK® guide 5th ed. Page 355.
30 B
Ref: PMBOK® guide 5th ed. Page 365.
31 C
Ref: PMBOK® guide 5th ed. Page 365.
32 D
Ref: PMBOK® guide 5th ed. Page 365.
33 A
Ref: PMBOK® guide 5th ed. Page 356.
34- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 366-367.
35 B
Ref: PMBOK® guide 5th ed. Page 367.
36- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 368.
37- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 368.
38- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 368.
39 D
Ref: PMBOK® guide 5th ed. Page 368.
40 C
Ref: PMBOK® guide 5th ed. Page 369.
41 B
Ref: PMBOK® guide 5th ed. Page 369.
Explanation: Copyright is an intellectual property.
42 C
Ref: PMBOK® guide 5th ed. Page 374.
43 A
Ref: PMBOK® guide 5th ed. Page 375.
44- 4(A, C, D)
Ref: PMBOK® guide 5th ed. Page 375.
45 A
Ref: PMBOK® guide 5th ed. Page 357.
46- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 375-376.
47 C
Ref: PMBOK® guide 5th ed. Page 377-Agreements.
48- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 377-Agreements.
49 D
Ref: PMBOK® guide 5th ed. Page 377-Agreements and Procurement negotiations.
50 D
Ref: PMBOK® guide 5th ed. Page 378.
51 A
Ref: PMBOK® guide 5th ed. Page 378.
52 B
Explanation: Alternative dispute resolution is a way to solve issues, out of court.
Conciliation, mediation, and arbitration are alternative dispute resolution methods.
53- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 381.
54 D
Ref: PMBOK® guide 5th ed. Page 378, 381.
55- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 381.
56 A
Ref: PMBOK® guide 5th ed. Page 381.
57 A
Ref: PMBOK® guide 5th ed. Page 228.
58- 4 (A,B,C,D)
Ref: PMBOK® guide 5th ed. Page 235.
59- 2(A,B)
60 C
Ref: PMBOK® guide 5th ed. Page 383.
61- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 384.
62 A
Ref: PMBOK® guide 5th ed. Page 384.
63- 4(None of the above)
Ref: PMBOK® guide 5th ed. Page 387.
Explanation: All of the above are true for early contract terminations.
64 A
Ref: PMBOK® guide 5th ed. Page 387.
65 C
Ref: PMBOK® guide 5th ed. Page 388-Procurement negotiations.
66 A
Ref: PMBOK® guide 5th ed. Page 393-Identify Stakeholders.
67- 2(A, B, D)
Ref: PMBOK® guide 5th ed. Page 394.
In some cases, residents protest and prevent the dam construction from starting hence influencing the project.
68- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 394.
69- 4(All of the above)
70 B
Ref: PMBOK® guide 5th ed. Page 397.
71 C
Ref: PMBOK® guide 5th ed. Page 397.
72 C
Ref: PMBOK® guide 5th ed. Page 398.
73 A
Ref: PMBOK® guide 5th ed. Page 398.
74-4 (All of the above)
Ref: PMBOK® guide 5th ed. Page 398.
75- 2(A, C)
Ref: PMBOK® guide 5th ed. Page 401.
76- 4(A, B, D)
Ref: PMBOK® guide 5th ed. Page 402.
77 B
Ref: PMBOK® guide 5th ed. Page 397.
78 A
Ref: PMBOK® guide 5th ed. Page 397.
79- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 403.
80- 3(All of the above)
Ref: PMBOK® guide 5th ed. Page 357.
81 D
Ref: PMBOK® guide 5th ed. Page 405.
82- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 407.
83- 3(C)
Ref: PMBOK® guide 5th ed. Page 357.
84 A
Ref: PMBOK® guide 5th ed. Page 406.
85- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 408
86 C
Ref: PMBOK® guide 5th ed. Page 228.
87 A
Ref: PMBOK® guide 5th ed. Page 228.
88 B
Ref: PMBOK® guide 5th ed. Page 228.
89 C
Ref: PMBOK® guide 5th ed. Page 228.
90 A
Ref: PMBOK® guide 5th ed. Page 228.
91- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 229.
92 A
Ref: Wikipedia
93 A
Ref: Wikipedia
94 C
Ref: PMBOK® guide 5th ed. Page 229.
95 C
Ref: PMBOK® guide 5th ed. Page 231.
96 D
Ref: PMBOK® guide 5th ed. Page 235.
97- 3(All of the above)
Ref: PMBOK® guide 5th ed. Page 357
98- 2(A, B)
Ref: PMBOK® guide 5th ed. Page 235.
99- 3(All of the above)
Ref: PMBOK® guide 5th ed. Page 357
100 A
Ref: PMBOK® guide 5th ed. Page 237.
101- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 237.
102 A
Ref: PMBOK® guide 5th ed. Page 359
103 B
Ref: PMBOK® guide 5th ed. Page 238.
104 B
Ref: PMBOK® guide 5th ed. Page 238.
105 B
Ref: PMBOK® guide 5th ed. Page 361
106 B
Ref: PMBOK® guide 5th ed. Page 238.
107 B
Ref: PMBOK® guide 5th ed. Page 239.
108 C
Ref: PMBOK® guide 5th ed. Page 240.
109 A
Ref: PMBOK® guide 5th ed. Page 240.
110 B
Ref: PMBOK® guide 5th ed. Page 242.
111 C
Ref: PMBOK® guide 5th ed. Page 245., Google.com results
112 D
Ref: PMBOK® guide 5th ed. Page 247.
113 B
Ref: PMBOK® guide 5th ed. Page 360
114 C
Ref: PMBOK® guide 5th ed. Page 250, 252.
115- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 66.
116 C
Ref: PMBOK® guide 5th ed. Page 67.
117 A
Ref: PMBOK® guide 5th ed. Page 68.
118 D
Ref: PMBOK® guide 5th ed. Page 68.
119- 3(A,D)
Ref: PMBOK® guide 5th ed. Page 242.
120- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 68.
121- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 84.
122- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 85.
123- 4(All of the above)
Ref: PMBOK® guide 5th ed. Page 85.
124 C
Ref: PMBOK® guide 5th ed. Page 85.
125- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 96.
126 C
Ref: PMBOK® guide 5th ed. Page 96.
127 B
Ref: PMBOK® guide 5th ed. Page 97.
128 D
Ref: PMBOK® guide 5th ed. Page 97.
129- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 105-106.
130 D
Ref: PMBOK® guide 5th ed. Page 109-110.
131- 4(A, B, C, D)
Ref: PMBOK® guide 5th ed. Page 110.
132 B
Ref: PMBOK® guide 5th ed. Page 112.
133 D
Ref: PMBOK® guide 5th ed. Page 112.
134 B
Ref: PMBOK® guide 5th ed. Page 112.
135 B
Ref: PMBOK® guide 5th ed. Page 112.
136 B
Ref: PMBOK® guide 5th ed. Page 112.
137 B
Ref: PMBOK® guide 5th ed. Page 114.
138 C
Ref: PMBOK® guide 5th ed. Page 114.
139 C
Ref: PMBOK® guide 5th ed. Page 114.
140 A
Ref: PMBOK® guide 5th ed. Page 114.
141 D
Ref: PMBOK® guide 5th ed. Page 114.
142- 3(A, B, C)
Ref: PMBOK® guide 5th ed. Page 114.
143 A
Ref: PMBOK® guide 5th ed. Page 115.
144 A
Ref: PMBOK® guide 5th ed. Page 115.
145 B
Ref: PMBOK® guide 5th ed. Page 115.
146 B
Ref: PMBOK® guide 5th ed. Page 116.
147- 2(A, B, C)
Ref: PMBOK® guide 5th ed. Page 362
148 C
Ref: PMBOK® guide 5th ed. Page 119.
149 D
Ref: PMBOK® guide 5th ed. Page 124.
150 A
Ref: PMBOK® guide 5th ed. Page 131.
151 A
Ref: PMBOK® guide 5th ed. Pg 147
152 D
Ref: PMBOK® guide 5th ed. Page 153.
153 D
Ref: PMBOK® guide 5th ed. Page 157.
154 D
Ref: PMBOK® guide 5th ed. Page 158.
155 C
Ref: PMBOK® guide 5th ed. Page 158.
156 D
Ref: PMBOK® guide 5th ed. Page 159.
157 C
Ref: PMBOK® guide 5th ed. Page 163.
158 D
Ref: PMBOK® guide 5th ed. Page 163.
159 A
Ref: PMBOK® guide 5th ed. Page 170.
160 B
Ref: PMBOK® guide 5th ed. Page 171.
Triangular Distribution time estimate = (Optimistic time estimate + Most likely time estimate + Pessimistic time estimate) / 3
(2+4+6)/3=4.”
161 C
Ref: PMBOK® guide 5th ed. Page 355.
162 D
Ref: PMBOK® guide 5th ed. Page 171.
Triangular Distribution time estimate = (Optimistic time estimate + Most likely time estimate + Pessimistic time estimate) / 3
Since the pessimistic estimate is not provided, the expected duration cannot be determined using the triangular distribution.”
163 B
Ref: PMBOK® guide 5th ed. Page 171.
Beta Distribution (from the traditional PERT technique) Time estimate = (Optimistic time + (4*Most likely time) + Pessimistic time) / 6
For the above question, Time estimate=(2+4(4)+6)/6=4.”
164 D
Ref: PMBOK® guide 5th ed. Page 171.
Beta Distribution (from the traditional PERT technique) Time estimate = (Optimistic time + (4*Most likely time) + Pessimistic time) / 6
For the above question, Time estimate=(2+4(4)+6)/6=4 which is not an option above.”
165 D
Ref: PMBOK® guide 5th ed. Page 171.
Beta Distribution (from the traditional PERT technique) Time estimate = (Optimistic time + (4*Most likely time) + Pessimistic time) / 6
For the above question, the most likely estimate is not provided and hence the expected duration cannot be calculated using beta distribution.”
166 C
Explanation: The time taken for each of the paths is as follows:
ABCDE?5d+5d+2d+1d=13d
AFGCDE?2d+3d+1d+2d+1d=9d
AHIDE?4d+6d+3d+1d=14d
Since AHIDE is the path with the longest duration, it is the critical path for this project.
167 A
Explanation: The time taken for each of the paths is as follows:
ABCDE?5d+5d+2d+1d=13d
AFGCDE?2d+3d+1d+2d+1d=9d
AHIDE?3d+6d+3d+1d=13d
Since AHIDE and ABCDE take the same time to complete and are the longest paths, they are the critical paths for this project.
168 C
Ref: PMBOK® guide 5th ed. Page 362
169 C
Explanation: Both activities B and C have to be completed before activity D can start. Activity C ends on Mar 8 (EF). Activity B ends on Mar 9 (EF). Since the latest EF is Mar 9, D can start only on Mar 10.
170 A
Explanation: The duration of activity A is 4 days. If activity A starts on Mar 3, it will finish by end of day, Mar 6. Hence EF date is Mar 6.
171 A
172 B
Ref: PMBOK® guide 5th ed. Page 363.
173 B
Explanation: PMBOK® guide 5th ed. Page 178.
174 C
Explanation: PMBOK® guide 5th ed. Page 178.
175 A
Explanation: PMBOK® guide 5th ed. Page 178.
176 D
Explanation: PMBOK® guide 5th ed. Page 179.
177 C
Ref: PMBOK® guide 5th ed. Page 363.
178 D
Explanation: PMBOK® guide 5th ed. Page 180.
179 A
Explanation: PMBOK® guide 5th ed. Page 181.
180 B
Explanation: PMBOK® guide 5th ed. Page 181.
181 D
Ref: PMBOK® guide 5th ed. Page 363.
182 D
Explanation: PMBOK® guide 5th ed. Page 181.
183- 3(Both A and B)
Explanation: PMBOK® guide 5th ed. Page 181.
184- 3(A, B, C)
Explanation: PMBOK® guide 5th ed. Page 182.
185- 2(A, B)
Explanation: PMBOK® guide 5th ed. Page 184.
186- 4(A, B, C, D)
Explanation: PMBOK® guide 5th ed. Page 182.
187 A
Explanation: PMBOK® guide 5th ed. Page 197.
188 A
Explanation: PMBOK® guide 5th ed. Page 201.
189 D
Explanation: PMBOK® guide 5th ed. Page 204.
190- 2(A, B)
Explanation: PMBOK® guide 5th ed. Page 204-205.
191- 4(A, B, C, D)
Explanation: PMBOK® guide 5th ed. Page 208.
192- 2(None of the above)
Explanation: PMBOK® guide 5th ed. Page 216.
All of the above are included in project cost control.
193 B
Explanation: PMBOK® guide 5th ed. Page 220.
EAC = AC + (BAC – EV)
EAC=1000+1200-900=$1300.
194 B
Explanation: PMBOK® guide 5th ed. Page 220.
EAC = BAC / CPI
EAC=1200/1.2=$1000
195 B
Ref: PMBOK® guide 5th ed. Page 363.
196- 3(A,D)
Ref: PMBOK® guide 5th ed. Page 242.
197 D
Explanation: PMBOK® guide 5th ed. Page 8.
198 C
Explanation: PMBOK® guide 5th ed. Page 8.
199 D
Explanation: PMBOK® guide 5th ed. Page 8.
200 B
Explanation: PMBOK® guide 5th ed. Page 9.
Dear La,
ReplyDeleteThanks for sharing these invaluable questions, they are really of big help.
Please check response for question 43. It seems option B is more pertinent to the question.
Thanks