Questions 121-140

121) Which of the below are true about deliverables?
A. A unique and verifiable product that is required to be produced to complete a process
B. Tangible components completed to meet the project objectives
C. Can include elements of the project management plan
D. Capability to perform a service that is required to be produced to complete a phase

Answer choices:
1. A
2. B
3. C
4. All of the above

122) Which of the below are examples of work performance data?
A. Work completed
B. Key performance indicators
C. Actual costs
D. Number of change requests

Answer choices:
1. A
2. B
3. C
4. All of the above

323) Which of the below could change requests include?
A. Corrective action
B. Preventive action
C. Defect repair
D. Updates

Answer choices:
1. A
2. B
3. C
4. All of the above

124) Which of the below is true about requests for change?
A. They cannot be indirect
B. They cannot be internally initiated
C. They can be contractually mandated
D. They can only be optional

125) Which of the below are functions of the change control board?
A. Review change requests
B. Record change decisions
C. Delay change requests
D. Evaluate change requests

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

126) Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, labeling products and documents, managing changes, and maintaining accountability are all part of which of the below?
A. Configuration audit
B. Configuration status accounting
C. Configuration identification
D. Configuration verification 

127) Recording and reporting a list of approved configuration identification, status of proposed changes to the configuration, and the implementation status of approved changes is done as part of which of the below?
A. Configuration audit
B. Configuration status accounting
C. Configuration identification
D. Configuration verification 

128) Ensuring that the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented is done as part of which of the below?
A. Configuration setup
B. Configuration status accounting
C. Configuration identification
D. Configuration verification and audit

129) Which of the below is true about project scope and product scope? Choose the best answer.
A. Completion of the project scope is measured against the project management plan while completion of the product scope is measured against the product requirements
B. Product scope comprises the features and functions that characterize a product, service, or result while project scope comprises the work performed to deliver a product, service, or result with the specified features and functions
C. Project scope is sometimes viewed as including product scope
D. Work of the project should result in delivery of the specified product scope

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

130) Which of the below is not a component of the Project scope management plan?
A. Process that establishes how the WBS will be maintained and approved
B. Process to control how requests for changes to the detailed project scope statement will be processed
C. Process that specifies how formal acceptance of the completed project deliverables will be obtained
D. Process for communicating scope to stakeholders

131) Which of the below are components of the requirements management plan?
A. Requirements prioritization process
B. Product metrics
C. Traceability structure
D. Details on how requirements activities will be planned

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

132) Which of the below is not true of requirements?
A. They include capabilities to be met by the project
B. They need not be the foundation of the WBS
C. They include the documented needs of the sponsor
D. They should be recorded in enough detail to be included in the scope baseline

133) Which of the below is not a valid requirement classification?
A. Business requirements
B. Solution requirements
C. Transition requirements
D. Transactional requirements

134) Your project creates reports for your business users to run on a daily basis. The reports take too long to load and don’t satisfy the performance requirement. Which of the following requirement classifications does performance requirement fall under?
A. Quality requirements
B. Solution requirements
C. Transition requirements
D. Project requirements

135) Your project creates reports for your business users to run on a daily basis. The reports take too long to load and don’t satisfy the performance requirement. Which of the following requirement classifications does performance requirement fall under?
A. Quality requirements
B. Non-functional requirements
C. Transition requirements
D. Project requirements

136) Your project creates reports for your business users to run on a daily basis. The reports should display data according to the profile of the user logged in.  This security requirement should be captured as a?
A. Quality requirement
B. Non-functional requirement
C. Transition requirement
D. Project requirement

137) Which of the below is not a tool/technique to collect requirements?
A. Interview
B. Delphi
C. Facilitated workshop
D. Focus group

138) Joint application design/development (JAD) session used in the software industry is an example of:
A. Interview
B. Delphi
C. Facilitated workshop
D. Focus group

139) Quality function deployment (QFD) used in the manufacturing industry is an example of:
A. Interview
B. Delphi
C. Facilitated workshop
D. Focus group

140) Short, textual descriptions of required functionality developed during a requirements workshop are called:
A. User stories
B. User requirements
C. Meeting notes
D. Interviews