Questions 141-160

141) Which of the below is not true about user stories?
A. They describe the stakeholder who benefits from the feature
B. They describe what the stakeholder needs to accomplish
C. They describe the benefit to the stakeholder
D. They are widely used with waterfall method

142) Which of the below is/are true about facilitated workshops?
A. Help reconcile stakeholder differences
B. Improve communication between participants
C. Help discover issues earlier
D. Might take longer to define cross-functional requirements

Answer choices:
1. A
2. A, B
3. A, B, C
4. All of the above

143) A technique that enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or for prioritization is:
A. Nominal group technique
B. Brainstorming
C. Affinity diagram
D. Idea/mind mapping

144) Which of the below methods is used in reaching a group decision when using the Delphi technique?
A. Unanimity
B. Majority
C. Plurality
D. Dictatorship

145) Which of the following tools and techniques to collect requirements is most effective when audiences are varied, geographically dispersed, and where statistical analysis is appropriate?
A. Workshops
B. Questionnaires and Surveys
C. Interviews
D. Focus groups

146) For your project, you have decided to build a working model of the final product and revise it based on feedback from stakeholders.  The tool/technique you are using is:
A. Storyboard
B. Prototype
C. Benchmarking
D. Observation

147) You are planning to acquire resources from a vendor for your software project. Which of the below are enterprise environmental factors that can affect the planning?
A. Marketplace conditions
B. There are only few resources who are experts in the technology you plan to implement
C. Suppliers
D. Recent lay-offs 

Answer choices:
1. A, C, D
2. A, B, C
3. C, D, A
4. D, B, A

148) You prepare a grid to map requirements to the deliverables adding project objectives, owner, priority, requirement description, etc. You are preparing the:
A. Storyboard
B. Prototype
C. Requirement traceability matrix
D. Mapping document

149) Which of the below will not be in the project scope statement?
A. Description of what is in the scope of the project
B. Description of what is not in the scope of the project
C. Acceptance criteria
D. Risks

150) You have prepared a WBS but the total of the work at the lowest levels doesn’t roll up correctly to the higher levels. Which of the below rules haven’t been followed?
A. 100 percent rule
B. Rule of sums
C. Net sum rule
D. Total work rule

151) You are a new PM who has been assigned a project. You are trying to plan out the schedule for the project and seek help from other members who have been with the company for a long time and have worked on similar projects in the past. This tool/technique is called:
A. Expert judgment
B. Historical information
C. Meetings
D. Analytical estimation

152) Which of the following is not true about milestones?
A. A milestone is a significant point or event in a project
B. Milestones can be mandatory or optional
C. Milestones are similar to regular schedule activities with the same structure and attributes
D. Milestones have finite duration during which the activity is performed

153) Which of the below is not true about mandatory dependencies?
A. Mandatory dependencies are those that are legally or contractually required or inherent in the nature of the work
B. Mandatory dependencies often involve physical limitations
C. Mandatory dependencies are also sometimes referred to as hard logic or hard dependencies
D. Technical dependencies are always mandatory

154) Which of the below is not true about discretionary dependencies?
A. The project team determines which dependencies are discretionary during the process of sequencing the activities
B. Discretionary dependencies are established based on knowledge of best practices within a particular application area
C. Discretionary dependencies are also referred to as soft logic or preferential logic
D. Discretionary dependencies should be partially documented since they can create arbitrary total float values and can limit later scheduling options

155) During activity sequencing, you determine that your quality assurance team cannot test code until your development team completes development. This is:
A. A Mandatory dependency
B. A Discretionary dependency
C. An internal mandatory dependency
D. An internal dependency

156) Which of the below is not true about project schedule network diagrams?
A. It is a graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities
B. It is produced manually or by using project management software
C. It can include full project details 
D. It can have only one summary activity

157) Which of the below will not be present in a resource calendar?
A. Working days and shifts on which each specific resource is available
B. When identified project resources will be available during the project
C. Staffing policies 
D. How long identified project resources will be available during the project

158) Which of the below is not an example of a resource category?
A. Labor
B. Equipment
C. Material 
D. Skill level

159) You have to estimate the duration of the design activity for your project. You know that 20 drawings have to be created and it will take the architect 10 hours per drawing. You estimate that the design activity will take 200 hours. This is an example of:
A. Parametric estimating
B. Analogous estimating
C. Three-point estimating
D. Decision making

160) If for a remodeling project, the estimates are:
Optimistic estimate: 2 days
Pessimistic estimate: 6 days
Most likely estimate: 4 days

What is the expected duration using the triangular distribution?
A. 6 days
B. 4 days
C. 2 days
D. Cannot be determined with the data provided