Questions 101-120

101) Which of the below are part of the seven basic quality tools (7QC)?
A. Fishbone diagrams
B. Flowcharts
C. Pareto diagrams
D. Checksheets

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

102) You are trying to decide whether a product should be developed in-house or purchased from outside. You will do this in which of the below phases?
A. Plan Procurement management
B. Conduct Procurements
C. Independent estimates
D. Proposal Evaluation

Answer choices:
1. A
2. B
3. All of the above
4. None of the above

103) The control chart below indicates that:

A. The process is stable
B. Corrective action should be taken as the process is out of control
C. Variations are in the normal range
D. No corrections are needed to the control parameters

104) The control chart below indicates that:

A. The process is stable
B. Corrective action should be taken as the process is out of control
C. Variations are in the normal range
D. No corrections are needed to the control parameters

105) You are managing a landscaping project. You have received bids from multiple agencies. Which of the below will you use to determine which bids are reasonable?
A. Agency’s timelines
B. Activity cost estimates
C. Contracts
D. Agency reputation

106) Which of the following are not true about scatter diagrams?
A. They are also called correlation charts
B. They seek to explain a change in the independent variable, in relationship to a change observed in the corresponding dependent    variable
C. If correlation can be established between the dependent and independent variable, a regression line can be calculated
D. A pattern of correlation may not exist between the variables

107) Which of the following is not true about Design of Experiments?
A. It is used to reduce the sensitivity of product performance to sources of variations caused by environmental or manufacturing    differences
B. It provides a statistical framework for systematically changing each of the important factors, rather than changing all the    factors one at a time
C. It plays a role in optimizing products or processes
D. Analysis of the experimental data should provide the optimal conditions for the product or process, highlight the factors that    influence the results, and reveal the presence of interactions and synergy among the factors

108) 100 light bulbs were chosen from a lot of 10,000 and were tested for life expectancy and two were found defective. This technique of quality planning is called:
A. Design of experiments
B. Force field analysis
C. Statistical sampling
D. Pareto diagram

109) Architects and engineers can use which of the following techniques to determine which combination of aesthetics and usability will produce the most liveable home at reasonable cost?
A. Design of experiments
B. Force field analysis
C. Statistical sampling
D. Pareto diagram

110) You are developing a reporting system for your stakeholders sourcing finance data. Given the need for accuracy, the stakeholders have mentioned that they want your reporting system to reconcile with the source systems’ finance data (revenue $) with an allowable variation of +/-0.05%. 0.05% is the:
A. Defect frequency
B. Tolerance
C. Measurement
D. Quality metric

111) The below diagram is called:

A. Force field analysis
B. Affinity diagram
C. Process decision program charts
D. Tree diagrams

112) Which of the below are not true of quality audits?
A. They can confirm the implementation of approved change requests
B. They can proactively offer assistance in a positive manner to improve implementation of processes to help the team raise    productivity
C. They may be scheduled or random
D. They may be conducted by only internal auditors

113) As part of your dam construction project you plan to resource some of the work externally. These components of work can be found in (choose the best answer):
A. RBS
B. WBS
C. Project management plan
D. Project scope statement

Answer choices:
1. A
2. B
3. All of the above
4. None of the above

114) Which of the following are not true about inspections?
A. They can be called peer reviews or walkthroughs
B. They are about keeping errors out of the hands of the customer
C. They cannot be done to validate defect repairs
D. The results of an inspection generally include measurements and may be conducted at a single activity or final product level

115) Develop Project Charter has the following benefits (Choose the best answer):
A. Well-defined project start
B. Well-defined project boundaries
C. Creation of a formal record of the project
D. Direct way for senior management to formally accept and commit to the project

Answer choices:
1. A
2. A, B
3. A, B, C
4. A, B, C, D

116) Which of the following is not true about a project charter?
A. Used to establish internal agreements within an organization
B. Once approved, formally initiates the project
C. Should be authored by the buying entity
D. Provides the project manager with the authority to plan and execute the project

117) Who from the below does not initiate a project?
A. Project Manager
B. Sponsor
C. Project management office staff
D. Portfolio governing body chairperson

118) Which of the below is not present in a project statement of work (SOW)?
A. Business need
B. Product scope description
C. Strategic plan
D. Request for proposal

119) Which of the below is/are true about tolerance?
A. Is an allowable variation to a metric
B. Is a project attribute
C. Is the same as measurement
D. Can be expressed as a percentage

Answer choices:
1. A, B
2. B, C
3. A, D
4. C, D 

120) An organization’s business needs can be based on which of the below?
A. Market demand
B. Ecological impacts
C. Legal requirement
D. Social need

Answer choices:
1. A, B, D
2. B, D, A
3. None of the above
4. All of the above